CSP-11 CSP-11 D2.13 · Domain 2 · Program Management · 25%

RACI

A plant shutdown plan assigns both the maintenance manager and contractor supervisor as Accountable for the same isolation-release decision. Each expects the other to confirm readiness. Before work proceeds, how should you define the deliverable, decision owner and required verification?

Updated . Independent CSP-11 practice. Not BCSP-endorsed. No pass guarantee.

Decision rule

One person is Accountable. Many may be Responsible. Confusion here is a control failure.

RACI: Responsible does the work, Accountable owns the outcome, Consulted before, Informed after.

In 20 seconds

  • One person is Accountable.
  • Many may be Responsible.
  • Confusion here is a control failure.
  • RACI clarifies Responsible, Accountable, Consulted, Informed for each critical activity.

How to apply RACI

THEORY: Single-point accountability. Two Accountables is zero Accountables. RACI does not replace competence. CALC: None. FIELD: MOC with three ‘accountable’ names and no one who can say no. Name one Accountable with authority to stop start-up. ASSESS: Putting the CSP as Informed only on a high-risk change is a design choice to review.

Worked case

Wrong first move: add more names to share blame. Correct move: one Accountable, named Responsible doers, consult specialists before authorize.

Why the rule holds

Related: 22, 34, 31.

Same rule, different setting

A well-control matrix lists five Accountable names, including the CSP, the insurer, and “everyone.” A contractor is injured because nobody owned the barrier. You are the CSP. The question is what RACI allows.

A hoist matrix lists five Accountable names, including the CSP, the insurer, and “everyone.” A rigger is injured because nobody owned the lift. You are the CSP. The question is what RACI allows.

Picture / model

Map roles to specific outputs, test whether the decision owner has authority and resources, and define acceptance evidence at handover. Calculate a simple project network with explicit parallel work and show how a changed dependency changes available float.

Exam traps

Original SafePath contrasts for RACI. These are study traps, not recalled BCSP items.

TrapCorrect read
RDoes the task
AOne owner — yes/no and resources
CAdvice with dialogue — typical EHS on operations
IFYI, no veto

Field move

The safety role is typically consulted. The insurer is not accountable.

Scenarios

Scenario 1 · Fundamental · CSP-11 D2.13

A LOTO row lists A: CSP, superintendent, insurer, “everyone.” Best correction?

Best action: One A: the line/process owner who can stop work and allocate isolation resources; CSP typically C; insurer not A.

Why: Evaluate the best response. The lockout row lists the safety practitioner, the superintendent, the insurer, and everyone as accountable. The best correction names one accountable person: the line or process owner who can stop work and allocate isolation resources. The safety role is typically consu…

Scenario 2 · Applied Scenario · CSP-11 D2.13

Who is typically Accountable for specifying a guard on a new press purchase?

Best action: The engineering/operations owner of the purchase, with EHS Consulted on hierarchy.

Why: Evaluate the best response. The best accountable person for specifying a guard on a new press is the engineering or operations owner of the purchase, with the safety role consulted on the hierarchy. The safety role reviews the specification. It is not the accountable purchaser. The vendor fabricate…

Scenario 3 · Applied Scenario · CSP-11 D2.13

You are the CSP reviewing a live decision at a Gulf Coast chemical terminal. Operations proposes a convenience path. In a RACI matrix, what distinguishes a consulted person from an informed person?

Best action: C is two-way influence before the decision; I is one-way after.

Why: Evaluate the best response. The best distinction is that consulted is two-way influence before the decision, and informed is one-way after. Reversing the two roles puts notice before input. Informed does not get a veto, and consulted is not a joint sign-off. Informed does not have to approve the re…

If the stem says this

Stem signalBest direction
two people think they are Accountablename a single Accountable owner
a critical control has no Responsible partyassign Responsible and Accountable
contractor interfaces are unclearwrite host/contractor RACI
two answers workhigher hierarchy / system / design
org chart changed last weekrefresh RACI before assuming coverage

Check before you leave

  • ✓ RACI clarifies Responsible, Accountable, Consulted, Informed for each critical activity.
  • ✓ One Accountable owner — not a committee fog.
  • ✓ Responsible does the work; Accountable owns the outcome.
  • ✓ Gaps and overlaps in RACI create missed critical controls.
  • ✓ Update RACI after MoC and reorganizations.
  • ✓ Contractors need explicit RACI with the host.

Blueprint mapping

RACI is the SafePath study class for CSP-11 D2.13 inside CSP-11 Domain 2, Program Management (25%). A high-weight management domain focused on measuring performance, investigating incidents, managing change, building systems, leading people, controlling records and resources, and interpreting data.

SafePath uses the publicly posted CSP-11 outline as a study map. It does not reproduce official exam content, and it is not affiliated with or endorsed by BCSP or Pearson VUE.

Domain 2: Program Management

Practice / flashcards / formulas

More classes in Program Management

Nearby lessons mapped to the same CSP-11 domain.

CSP-11 D2.13

Other classes on this task

This is the only detailed SafePath lesson currently primary-mapped to CSP-11 D2.13.

RACI study questions

What decision does the RACI class train?
One person is Accountable. Many may be Responsible. Confusion here is a control failure. This is independent SafePath CSP practice for CSP-11 D2.13. It is not an official BCSP item and it is not a pass guarantee.
What exam trap shows up in RACI?
A common miss treats this as sufficient: R The stronger read is: Does the task
How does RACI map to the CSP-11 blueprint?
SafePath maps this class to CSP-11 D2.13 in Domain 2, Program Management (25% of the published blueprint). Use the public outline for study planning. SafePath is not affiliated with or endorsed by BCSP.